Advanced Estimating Engine
Build estimates that get smarter every job
Industry modules, saved production rates, regional cost adjustments, and crew-based modeling. Log actuals and the engine self-tunes.
Crew-based production model
Engine output
Concrete Crew installs ~35 CY/day. 500 CY ≈ 14.3 crew-days.
Region adjust: labor ×1.00 · material ×1.00
Crew-days14.3
Labor cost$62,857
Material cost$92,500
Total cost$155,357
Cost / CY$311
high confidence · 5 samples